Related Files
Status
The final ballot for the Inverter-Based Resource Glossary Term concluded 8 p.m. Eastern, Thursday, September 12, 2024. The voting results can be accessed via the links below.
The definition and its implementation plan will be submitted to the Board of Trustees for adoption and then filed with the appropriate regulatory authorities.
Background
The Federal Energy Regulatory Commission (FERC) issued Order No. 901 on October 19, 2023, which includes directives on new or modified NERC Reliability Standard projects. Order No. 901 addresses a wide spectrum of reliability risks to the grid from the application of inverter-based resources (IBR), including both utility scale and behind-the-meter or distributed energy resources. Within the Order, are four milestones that include sets of directives to NERC. NERC developed a
directive mapping document as part of its
workplan to address all aspects of Order No. 901. The
Milestone 3 projects will address deficiencies within the current state of model quality.
The NERC Inverter-based Resource (IBR) Performance Task Force (IRPTF) undertook an effort to perform a comprehensive review of all NERC Reliability Standards to determine if there were any potential gaps or improvements. The IRPTF identified several issues as part of this effort and documented its findings and recommendations in the “IRPTF Review of NERC Reliability Standards White Paper," which was approved in March 2020 by the Operating Committee and the Planning Committee (now part of the Reliability and Security Technical Committee (RSTC)). Among the findings noted in the white paper, the IRPTF identified issues with MOD-026-1 and MOD-027-1 that should be addressed. The RSTC endorsed the SAR on June 10, 2020.
Consistent with the IRPTF recommendations, the scope of the proposed SAR includes revisions to NERC Reliability Standards MOD-026-1 and MOD-027-1. Standards MOD-026-1 and MOD-027- 1 require, among other things, Generator Owners to provide verified dynamic models to their Transmission Planner for the purposes of power system planning studies. Both standards contain language that is specific to synchronous generators that is not applicable to IBRs. The IRPTF recommended revisions to clarify the applicable requirements for synchronous generators and IBRs. As such, the SAR proposes revisions to MOD-026-1 and MOD-027-1 to clarify requirements related to IBRs and to require sufficient model verification to ensure accurate generator representation in dynamic simulations. The Standards Committee accepted the SAR and authorized posting at its September 24, 2020 meeting.
Standard(s) Affected
–
MOD-026-1 Verification of Models and Data for Generator Excitation Control System or Plant Volt/Var Control Functions |
MOD-027-1 Verification of Models and Data for Turbine/Governor and Load Control or Active Power/Frequency Control Functions
Purpose/Industry Need
Project 2020-02 Transmission-connected Dynamic Reactive Resources SAR was posted from March 30 to May 13, 2020, and members of a SAR DT were solicited. However, Project 2020-02 was paused indefinitely, and a SAR DT was not appointed. Subsequently, a second SAR involving similar standards, namely MOD-026 and MOD-027, was being drafted by the IRPTF and approved for posting in September 2020 by the Standards Committee. The Project 2020-06 Verifications of Models and Data for Generators SAR will be posted for industry comment, and additional nominees with MOD-026/027 background will be sought. A single SAR DT will be charged with determining whether to combine the two projects and drafting a combined SAR.
See
Project 2020-02 Transmission-connected Dynamic Reactive Resources for additional purpose statement.
Subscribe to this project's observer mailing list
Select "NERC Email Distribution Lists" from the "Service" drop-down menu and specify “Project 2020-06 Verifications of Models and Data for Generators” in the Description Box.
Proposed Timeline for Order No. 901 Milestone 3 Project 2020-06:
Goal Date |
Latest Possible Date
| Action |
November 13, 2024
| N/A
| SC
meeting to authorize standard(s) drafting
|
January 15-16, 2025
| January 15-16, 2025
| Technical
Conference Phoenix, AZ
|
February 19, 2025
| February 19, 2025
| Waivers
to SC
|
March 1, 2025
| April 1, 2025
| Initial
draft prepared
|
March 1-17, 2025
| April
1-April 17, 2025
| Stakeholder
outreach
|
April 2025
| May
2025
| Submit
for SC agenda package
|
April-May, 2025
| June
14-July 14, 2025
| Initial
30-day comment period with ballot (15 days waiver)
|
May 15-26, 2025
| July
15-25, 2025
| DT drafting
|
May 29-June 18, 2025
| July
30-August 18, 2025
| Additional
20-day comment period with ballot (waiver)
|
June 20-27, 2025
| August
19-26, 2025
| DT drafting
|
July 7-16, 2025
| September
9-22, 2025
| Final
Ballot (5 days waiver)
|
August 2025
| October
1, 2025
| NERC
BOT
|