Project 2021-03 CIP-002

​​​​​​​​​​​​​​​​​​​​​​​​​​Related Files

Status
A formal comment period for draft two of CIP-002-Y Cyber Security BES Cyber System Categorization is open through 8 p.m. Eastern, Thursday, May 16, 2024​. Additional ballots for the standard and implementation plan, as well as a non-binding poll of the associated Violation Risk Factors and Violation Severity Levels will be conducted May 7 – 16, 2024
.

Background/Purpose

The Standards Committee (SC) has tasked the Project 2021-03 standard drafting team (SDT) with the following:

  1. Transmission Owner Control Centers (TOCCs) – The SC assigned a portion of the Project 2016-02 SAR that relates to TOCCs to the Project 2021-03 SDT. That SAR portion is to review CIP-002 and evaluate the categorization of TOCCs performing the functional obligations of a Transmission Operator, specifically those that meet medium impact criteria. In addition, this SDT is assisting NERC staff in meeting the directive from the NERC Board of Trustees to conduct further study of the need to readdress the applicability of the Critical Infrastructure Protection Reliability Standards to these Control Centers to support reliability. To help meet this directive and the scope of the SAR, the SDT initiated a field test. The SC approved the Project 2021-03 Field Test Plan on November 17, 2021. There were three field tests conducted and the SDT is working on modifications to the CIP-002 Criterion 2.12 and the Control Center definition.

  2. CIP-002 and CIP-014 – This SAR provides revisions to CIP-002 and CIP-014 to clarify the responsibility of Reliability Coordinators, Planning Coordinators, and Transmission Planners in identifying Facilities that warrant consideration under these Reliability Standards. As it relates to the Transmission Planner and Planning Coordinator functions, the language “critical to the derivation of Interconnection Reliability Operating Limits (IROLs)" should be replaced/updated to appropriately identify Facilities that, if somehow compromised, could significantly impact the reliability of the Bulk Electric System (BES). Additionally, this SAR includes a review of the applicability of Facilities identified by the Reliability Coordinator as critical to the derivation of IROLs to CIP-002 and CIP-014. The SC accepted this SAR on July 21, 2021.

  3. CIP-002 SAR for Requirement R1 Parts 1.1 – 1.3 – This Standard Authorization Request is to consider if such a protocol converter meets the definition of a BES Cyber Asset by having an adverse impact to one or more facilities and the reliable operation on the BES. This includes consideration to the threat of unavailability, degradation, or misuse to a connected BES Cyber System and the aggregation of serial system-to-system communications from substations to Control Center BES Cyber Systems. As such, this project supports reliability by clarifying how these protocol converters should be categorized and if they are to reside within a defined Electronic Security Perimeter.

  4. CIP-002 – This SAR seeks to revise CIP-002 to include identification and categorization of certain Cyber Assets (Electronic Access Control or Monitoring Systems, Physical Access Control Systems, and Protected Cyber Assets) associated with high and medium impact BES Cyber Systems. The SC accepted this SAR on November 17, 2021. The Project 2021-03 SDT originally included nine members, but now the team is down to five SDT members. The three supplemental SDT members would assist project 2021-03 in completing the remaining three SARs assigned to this project.

Standard(s) Affected CIP-002: Cyber Security – BES Cyber System Categorization and CIP-014: Physical Security


​​Draft

Ac​tions

Dates

Results​
​Consideration of Comments
​​Draft 2

CIP-002-Y
Clean​ | Redline to Last Posted | Redline to Last Approved​

Implementation Plan

Supporting Materials

Unofficial Comment Form (Word)

Technical Rationale
Additional Ballots and Non-binding Poll

Info

Vote


05/07/24 - 05/16/24
​Comment Period

Info

Submit Comments​


04/02/24 - 05/16/24

​​Draft 1


CIP-002-Y

CleanRedline

Implementation Plan

Supporting Materials

Unofficial Comment Form (Word)

Technical Rationale

Initial Ballots and Non-binding Poll

Ballot Open Reminder​

Info

Vote




10/31/23 - 11/09/23​

Ballot Results




​Join Ballot Pools
​09/26/23 - 10/25/23


​Comment Period

Info

Submit Comments​


09/26/23 - 11/09/23​
​​


​​Supplemental Drafting Team Nominations

Supporting  Materials

Unofficial Nomination Form​​ (Word)
Nomination Period

Info

Submit Nominations​


07/20/23 - 08/18/23

​CIP-002-5.1a Criterion 1.3 Revision SAR

Supporting Materials

Unofficial Comment Form (Word)
​Comment Period

Info

Submit Comments​


07/20/23 - 08/18/23




Unofficial Comment Form (Word)


Comment Period

Info​
​​
Submit Comments


06/13/23 - 07/12/23


CIP-002 Communications Protocol Converters SAR

Supporting Materials

Unofficial Comment Form (Word)​



Comment Period

Info

Submit Comments​



03/02/23 - 03/31/23







​Field Test Final Report​


​​For informational purposes

Standard Authorization Requests

Modifications_to_CIP-002

CIP-002-5.1a_and_CIP-014-2


Supporting Materials

Unofficial Comment Form (Word)​



Comment Period

Info

Submit Comments






11/22/22 - 12/21/22




​Field Test Third Questionnaire

CIP-002 TOCC Field Test Questionnaire 3​
The questionnaire was sent to the field test participants on September 14, 2022
09/14/22 - 10/04/22
​​Supplemental Drafting Team Nominations

Supporting  Materials

Unofficial Nomination Form
Nomination Period

Info​

Submit Nominations​​


05/23/22 - 06/22/22




Request for Interpretation CIP-002-5.1a SAR
The Standards Committee rejected the CIP-002-5.1a – Serial Communications Request For Interpretation (RFI) submitted by Burns & McDonnell on February 22, 2023

Modifications to CIP-002 SAR

The Standards Committee accepted the SAR on
February 16, 2022

Field Test Second Questionnaire

CIP-002 TOCC Field Test Questionnaire 2

Power Flow Instruction Document

The questionnaire was sent to the field test participants on
February 22, 2022



02/22/22 - 04/01/2
2
Summary of Responses Received
(Questionnaire
1 and 2)​
Field Test First Questionnaire​

CIP-002 TOCC Field Test Questionnaire 1

The questionnaire was sent to the field test participants on January 10, 2022

0​
1/10/22 - 02/07/22
Summary of Responses Received
(Questionnaire
1 and 2)​


CIP-002 TOCC Field Test Plan​
The Standards Committee approved the Field Te​st Plan on November 17, 2021​



CIP-002 and CIP-014​ SAR​
​The Standards Committee accepted the SAR on July 21, 2021​​


​​
2016-02 SAR​
​The Standards Committee accepted the SAR on March 17, 2021
​Drafting Team Nominations

Supporting​ Materials

Unofficial Nomination Form (Word)

Nomination Period
Info​
(updated)

Submit Nominations 

03/22/21 – 04/27/21 (extended)



 

​