Project 2010-09 Cyber Security Order 706B Nuclear Plant Implementation Plan
Related Files

Status:
The Cyber Security 706b Nuclear Implementation Plan was approved by the Board of Trustees on August 5, 2010 and will be filed for approval with regulatory authorities.

Purpose/Industry Need:
 
In Order 706-B, FERC provided the following determination:

59. The Commission finds that it is not appropriate to dictate the schedule contained in Table 3 of NERC’s Implementation Plan, i.e., a December 2010 deadline for auditable compliance, for nuclear power plants to comply with the CIP Reliability Standards.  Instead of requiring nuclear power plants to implement the CIP Reliability Standards on a fixed schedule at this time, we agree to allow more flexibility.

60. Rather than the Commission setting an implementation schedule, we agree with commenters that the ERO should develop an appropriate schedule after providing for stakeholder input. Accordingly, we direct the ERO to engage in a stakeholder process to develop a more appropriate timeframe for nuclear power plants’ full compliance with CIP Reliability Standards. Further, we direct NERC to submit, within 180 days of the date of issuance of this order, a compliance filing that sets forth a proposed implementation schedule.  

Draft Action Dates Results Consideration of Comments
Draft Implementation Plan for Version 2 and 3 CIP Standards for Nuclear Power Plants
 
Revised Implementation Plan (V2)
 
Revised Implementation Plan (V3)
Recirculation Ballot Vote>>  | Info>>
6/22/2010 - 7/2/2010
(closed)
 
 
Initial Ballot
 
5/19/2010 - 6/1/2010
(closed)
Consideration of Comments>>
Pre-ballot Review
4/19/2010 - 5/19/2010
(closed)
   
 
Draft Implementation Plan for Version 2 and 3 CIP Standards for Nuclear Power Plants
 
Revised Implementation Plan (V2)
 
Revised Implementation Plan (V3)
 
Supporting Materials:
Comment Period
 ​

 
2/12/2010 - 3/15/2010
(closed)
Comments Received>> Consideration of Comments>>
 
Order 706-B Nuclear Implementation Plan for CIP Standards
 
Implementation Plan
Recirculation Ballot
 
9/1/2009 - 9/10/2009
(closed)
 
Initial Ballot
 
8/19/2009 - 8/28/2009
(closed)
 
Consideration of Comments>>
Order 706-B Nuclear Implementation Plan for CIP Standards Posted for a Shortened Comment Period and Pre-ballot Review Period
 
 
Supporting Materials:
Shortened Pre-ballot Review and
Comment Period
 
7/20/2009 - 8/14/2009
(closed)

Consideration of Comments>>

To download a file click on the file using your right mouse button, then save it to your computer in a directory of your choice.