Project 2007-17.4 PRC-005 FERC Order No. 803 Directive

Related Files 

Status
A final ballot for PRC-005-6– Protection System, Automatic Reclosing, and Sudden Pressure Relaying Maintenance concluded 8 p.m. Eastern, Monday, October 26, 2015. The ballot results can be accessed via the links below. The standard will be submitted to the Board of Trustees for adoption and then filed with the appropriate regulatory authorities.

Background
FERC approved Standard PRC-005-3 and, in Paragraph 31, directed NERC to:
"...direct that, pursuant to section 215(d)(5) of the FPA, NERC develop modifications to PRC-005-3 to include supervisory devices associated with auto-reclosing relay schemes to which the Reliability Standard applies. Further, we clarify that NERC’s proposal regarding the scope of supervisory devices is an acceptable approach to satisfy the Commission directive. Specifically, NERC proposed in its NOPR comments, and we find acceptable, that the scope of the supervisory devices to be encompassed in the Reliability Standard are those providing voltage supervision, supervisory inputs associated with selective auto-reclosing, and sync-check relays that are part of a reclosing scheme covered by PRC-005-3."
 
In addition, NERC filed a petition for approval of PRC-005-4 on December 18, 2014 and currently a notice of proposed rulemaking has been issued by FERC pending comments due back form industry by June 15, 2014.

PRC-005-5 was adopted by the Board on May 7, 2015 and is pending regulatory filing.
· PRC-005-3 – Project 2007-17.2 PRC-005 Protection System Maintenance and Testing – Phase 2 (Reclosing Relays)
· PRC-005-4 – Project 2007-17.3 (PRC-005-X) Protection System Maintenance and Testing – Phase 3 (Sudden Pressure Relays)
· PRC-005-5 – Project 2014-01 Standards Applicability for Dispersed Generation Resources
 
Standard(s) Affected: PRC-005-3 - Protection System and Automatic Reclosing Maintenance

Purpose/Industry Need
Provide clear, unambiguous requirements and standard(s) to address the directive in FERC Order 803.

Draft Actions Dates Results Consideration of Comments


Draft 1

PRC-005-6
Clean | Redline to Last Posted

Redline to Last Approved (PRC-005-5)

Implementation Plan
Clean | Redline to Last Posted

Implementation Plan Rationale
Clean | Redline to Last Posted

Supporting Materials

Standard Authorization Request
Clean | Redline to Last Posted

Supplementary Reference and FAQ
Clean | Redline to Last Posted

Consideration of Directives
Clean | Redline to Last Posted

​Final Ballot

Info

Vote
​10/15/15 - 10/26/15 Summary

Ballot Results​

Draft 1

PRC-005-6
Clean | Redline to Last Approved (PRC-005-5)

Implementation Plan
Clean | Redline to Last Posted

Implementation Plan Rationale

Supporting Materials

Unofficial Comment Form (Word)

Standard Authorization Request
Clean | Redline to Last Posted

VRF/VSL Justification
Clean | Redline to Last Approved

Supplementary Reference and FAQ
Clean | Redline to Last Posted

Consideration of Directives




Draft RSAW






Initial Ballot and Non-binding Poll

Updated Info

Info

Vote

​09/04/15 - 09/16/15 Summary

Ballot Results

Non-binding Poll Results​
Comment Period

Info

Submit Comments
​07/30/15 - 09/16/15 Comments Received Consideration of Comments​

Join Ballot Pools
​07/30/15 - 08/28/15




Info

Send RSAW feedback to:

RSAWfeedback@nerc.net


08/13/15 - 09/16/15​
Second Posting

SAR
 
Supporting Materials
 
 
VRF/VSL Justification
Clean | Redline to Last Approved
 
Supplementary Reference and FAQ
​Comment Period
 
 
06/11/15 - 07/10/15​ Comments Received​
 
 
Supporting Materials
 
 
 
 
Comment Period
 
 
3/12/15 - 4/10/15 Comments Received
 