Order 754
Related Files
 
Status
The Order No. 754 Data Request portal is closed for data reporting. The NERC System Protection and Control Subcommittee (SPCS) in conjunction with the NERC System Analysis and Modeling Subcommittee (SAMS) is preparing a report of the findings and conclusions. This report will be reviewed by the NERC Planning Committee (PC) for approval and should be finalized third quarter 2015.
 
 
Reporting Schedule
Period
Reporting Deadline
Activity
End of 1st month
October 5, 2012
Transmission Planners must acknowledge the request for data
End of 6th month
March 4, 2013
Transmission Planners must submit a status report stating percent of work complete
End of 12th month
October 2, 2013
Transmission Planners must report data for buses operated at 300 kV or higher
End of 18th month
March 3, 2014
Transmission Planners must report data for buses operated at 200 kV or higher and below 300 kV
End of 24th month
September 30, 2014
Transmission Planners must report data for buses operated at 100 kV or higher and below 200 kV


Background
The NERC Board of Trustees approved the Order No. 754 Request for Data or Information on August 16, 2012. The data request became effective September 1, 2012 and is applicable to each TP within the United States. While it is not mandatory for registered entities in Canada to respond, Canadian entities are strongly encouraged to submit data so that decisions regarding the concern stated in Order No. 754 can be based on complete data across North America.  Each Generator Owner, Distribution Provider, and Transmission Owner is required to support its TP in completing the steps necessary to obtain the data for reporting.

Summary

Order 754 is the Final Rule approving the interpretation of Interpretation TPL-002-0a PacifiCorp (Project 2009-14) regarding requirement R1.3.10. In addition to the approval, the Commission expressed concern about a single point of failure of protection systems and issued a directive for further investigation. From the Order, “…the Commission believes that there is an issue concerning the study of the non-operation of non-redundant primary protection systems; e.g., the study of a single point of failure on protection systems” (P19). In the first part of the directive (P20), the Commission directed FERC staff to meet with NERC and its appropriate subject matter experts to explore this reliability concern, including where it can best be addressed, and identify any additional actions necessary to address the matter. This portion of the directive was satisfied by the October 24-25, 2011 Technical Conference. In the second part (P20), NERC must complete an informational filing within six months of the Order (middle March 2012) explaining whether there is a further system protection issue that needs to be addressed and, if so, what forum and process should be used to address that issue and what priority it should be accorded relative to other reliability initiatives planned by NERC.

Purpose /Industry Need
T
he participants in the technical conference perceived a reliability concern regarding the comprehensive assessment of potential protection system failures by registered entities.  The group agreed on the need to study if a gap exists regarding the study and resolution of a single point of failure on protection systems. Note: This is not a “redundancy of protection systems” issue. The issue is, do the requirements in the transmission planning reliability standards adequately address the analysis and discovery of a protection system failure in order to develop plans to meet the performance requirements for the BES (i.e. TPL-001, 002, 003, and 004).

Draft Action Dates Results Consideration of Comments

Data Reporting

Data Reporting

 

Note: If you are a new data submitter, please send an email with your contact information to DataRequest754@nerc.net before registering for access

  

Register for Access to Order No. 754 Portal>> 

Closed 9/30/2014
No longer active 

 

 Returning Order No. 754 Portal Users>> 

Closed 9/30/2014
No longer active

 

Buses 300 kV and above
​9/3/2013 - 10/2/2013
(Closed, but entities may submit corrections)

Buses at 200 kV and below 300 kV
2/3/2014 - 3/3/2014
Extended to 3/6/2014 (Due to technical issues)

Buses at 100 kV and below 200 kV
9/1/2014 - 9/30/2014
(Available for submitting data)

Technical Support

Coverage Support
8-5 p.m., ET

Monday-Friday

To open an IT Help Desk ticket, email: support@nerc.net

Email must contain:
Requester's name
Company name
Phone number
Region
Description of issue
Name of application
(e.g., Order 754)

​Data Request
Six-month
Status Report

Unofficial Comment Form (Word)

​Reporting Period

Info>>

​1/28/2013-3/4/2013 Six-Month Status Report>>
 
 
Data Request Acknowledgement
30-day Acknowledgement Period

 
9/1/2012 - 10/5/2012 Acknowledgments
As of 9/30/2012

MS Excel>>>
 
 
General Questions and Answers
Submit a Question Via
9/1/2012 - 08/31/2014  
 
Requests for Clarifications and Responses

 

Data Reporting Template
 
Revised:
July 12, 2013
Final Board of Trustees
Supporting Documents
 
Order 754 Data Request
 
Final - Reporting Template
(Please see far right column for most current template)
Approval 8/16/2012 Approved  
Draft 2 - Webinar Slides 6/7/2012
 
Draft 2
 
 
 
Informal Comment Period
 
​ 
5/11/2012 - 6/25/2012 Comments Received>>
 
 
 
Draft 1 - Webinar #2 Slides 1/20/2012
Consolidated Q & A for Webinars 1 and 2
Draft 1 - Webinar #1 Slides 1/5/2012
 
Draft 1

Data Request

Data Reporting Template

Unofficial Comment Form
Informal Comment Period

Info>>
12/22/2011 - 2/6/2012


Consideration of Comments>>


Joint SPCS/TIS Meeting
Fort Worth, TX

Draft Presentation to Joint SPCS/TIS December 6-7, 2011


Draft Data Request O​utline
Draft Interpretation Request Form


Draft Suggestion Form
Agenda

  12/6/2011 - 12/7/2011 Final Drafts:

Presentation to Joint SPCS/TIS

Data Request

Interpretation Request Form

Interpretation Suggestion Form

Data Reporting Template
 
FERC Staff Meeting - Single Points of Failure on Protection Systems

FERC Technical Conference

Agenda

Notice of Staff Meeting
10/24/2011-10/25/2011

Slides
Technical Discussion Summary
To download a file click on the file using your right mouse button, then save it to your computer in a directory of your choice.
 

All comments should be forwarded to sarcomm@nerc.net.  ​​