Project 2021-01 System Model Validation with IBRs​

​​​​​​​​​​​​​​​​​​​​Related Files​

Status
Nominations are being sought for additional drafting team members through 8 p.m. Eastern, Friday, December 20, 2024. 
The Standards Committee is expected to appoint members to the drafting team in February 2025. Nominees will be notified shortly after they have been appointed.

Background
The Federal Energy Regulatory Commission (FERC) issued Order No. 901 on October 19, 2023, which includes directives on new or modified NERC Reliability Standard projects. Order No. 901 addresses a wide spectrum of reliability risks to the grid from the application of inverter-based resources (IBR), including both utility scale and behind-the-meter or distributed energy resources. Within the Order, are four milestones that include sets of directives to NERC. NERC developed a directive mapping document as part of its workplan to address all aspects of Order No. 901. The Milestone 3 projects will address deficiencies within the current state of model quality.

Project 2021-01 will address system-level model verification and validation against actual behavior during disturbances, as well as aligning steady state and dynamic representation, where appropriate. Additional focus will be to develop criteria for performing validation, determine minimum study conditions for conducting validation studies, and develop a process to communicate system interconnection-wide model defects to Transmission Planners and other associated entities.

To facilitate the development of this Milestone, Standard Authorization Requests were assigned to active projects that already had some aspects of Order No. 901-directed modeling improvements and drafting team familiarity with the Reliability Standards to be changed. Project 2021-01 Modifications to MOD-025 and PRC-019 will resume upon completion of this Milestone 3 project.

All Milestone 3 projects must be filed with FERC by November 4, 2025, with full implementation by January 1, 2030, to comply with Order No. 901.​​​

Standard(s) Affected – MOD-033-2 Steady-State and Dynamic System Model Validation

Purpose/Industry Need
The proposed revisions to MOD-033-2 are described in the SAR.

Subscribe to this project's observer mailing list
Select "NERC Email Distribution Lists" from the "Service" drop-down menu and specify “Project 2021-01 System Model Validation with IBRs​" in the Description Box.​

Proposed Timeline for Order No. 901 Milestone 3 Project 2021-01
The project timeline is shown below for industry awareness. This table will be updated with any changes as the project progresses.​​

Goal Date Latest Possible Date
Action
November 13, 2024
N/A
SC meeting to authorize standard(s) drafting
November 21, 2024 – December 20, 2024
N/A
30-day posting for supplemental drafting team nominations​
January 2025
February 2025
Submit NERC recommendations for supplemental drafting team for SC agenda package
January 15, 2025
February 19, 2025
SC to appoint supplemental members to Project 2021-01
January 15-16, 2025
January 15-16, 2025
Technical Conference Phoenix, AZ
February 19, 2025
February 19, 2025
Waivers to SC
March 1, 2025
April 1, 2025
Initial draft prepared
March 1-17, 2025
April 1-April 17, 2025
Stakeholder outreach and any revisions to be made from that outreach
March 17-27, 2025
April 17-28, 2025
Quality Review
March 28-April 3, 2025
April 28-May 3, 2025
DT Review of Quality Review inputs
​April 2025​
​May 2025
​Submit for SC agenda package
​April 13, 2025
​June 13, 2025
​Request authorization to post
​April-May, 2025​
​June 14-July 14, 2025​
​Initial 30-day comment period with ballot (5 or 10 days, depending on waiver)
​May 15-26, 2025
​July 15-25, 2025
​DT responses to comments
​May 26-May 28, 2025
​July 25-29, 2025
​Quality Review
​May 28-29, 2025
​July 29-30, 2025
​DT Review of Quality Review inputs
​May 29-June 18, 2025
​July 30-August 18, 2025
​Additional 20-day comment period with ballot (depending on waiver)
June 20-27, 2025
​August 19-26, 2025
​DT responses to comments
​June 27-29, 2025
​August 26-30, 2025
​Quality Review
​June 29-31, 2025
​September 1-2, 2025
DT Review of Quality Review inputs​
​July 7-16, 2025
​September 9-22, 2025
​Final Ballot (5-10 days depending on waiver)
​July 17-31, 2025
​September 23-29, 2025
​Final document prep and buffer
​August 2025
​October 1, 2025
​NERC BOT for adoption (may be a special call)
​​November 4, 2025
​November 4, 2025
File with FERC
 

 



Draft Actions Dates Results Consideration of Comments

Supplemental Drafting Team Nominations

Supporting Materials



Nomination Period


In​fo​

Submit Nominations​​​



11/21/24 - 12/20/24
Standard Authorization Request
The Standards Committee authorized standard(s) drafting on 
November 13, 2024.
Supplemental Drafting Team Nominations

Supporting Materials

Nomination Period

Info

Submit Nominations​​


08/15/2024 - 09/13/24​
​​Standard Authorization Request

Supporting Materials

Unofficial Comment Form (Word)
​Comment Period

Info

Submit Comments​


05/23/24 - 06/28/24




Consideration of Comments

Draft 2
MOD-025-3
Clean | Redline to Last Posted | Redline to Last Approved

PRC-019-3
Clean | Redline to Last Posted | Redline to Last Approved

MOD-025-3 Implementation Plan
Clean | Redline

PRC-019-3 Implementation Plan
Clean​ | Redline

Supporting Materials

Unofficial Comment Form (Word)

Technical Rationales
MOD-025-3
PRC-019-3​

VRF/VSL Justifications
MOD-025-3
PRC-019-3

Implementation Guidance for PRC-019-2​




Additional Ballots and Non-binding Polls

Ballot Open Reminder​

Info

Vote






05/30/23 - 06/08/23


​Comment Period

Info

Submit Comments​



04/25/23 - 06/08/23​





​Draft 1

MOD-025-3
Clean | Redline

PRC-019-3
Clean | Redline

Implementation Plans
MOD-025-3 
PRC-019-3

Supporting Materials

Unofficial Comment Form (Word)

Technical Rationales
MOD-025-3
PRC-019-3​

VRF/VSL Justifications
MOD-025-3
PRC-019-3





​Initial Ballots and Non-binding Polls

Updated Info​

Info


Vote








11/04/22 - 11/17/22
(extended)

Ballot Results

MOD-025-3​ Implementation Plan



Non-binding Poll Results



​​Join Ballot Pools
09/29/22 - 10/28/22​


​Comment Period

Info

Submit Comments​

09/29/22 - 11/17/22​ (extended)


MOD-025-2 SAR
Clean | Redline

PRC-019-2 SAR
Clean | Redline​


The Standards Committee accepted the SARs on December 15, 2021





Supplemental Drafting Team Nominations

Supporting Materials


Nomination Period

Info​

Submit Nominations​
04/30/21 - 05/20/21​
Drafting Team Nominations

Supporting Materials

Nomination Period

Info​

Submit Nominations
03/04/21 - 04/2/21​


MOD-025-2 SAR

PRC-019-2 SAR

Project 2020-02 SAR


Supporting Materials

Unofficial Comment Form (Word) 



Comment Period


Info​

Submit Comments


03/04/21 - 04/2/21​


Comments Received​



Consideration of Comments​