Related Files
Status
The formal comment period for draft one of EOP-012-3
Extreme Cold Weather Preparedness and Operations concluded 8 p.m.
Eastern, Tuesday, November 5, 2024. Comments received and ballot results can be accessed via the links below.
The drafting team will review all responses received during the comment period and determine the next steps of the project.
Background
NERC developed the original version of the generator cold weather preparedness Reliability Standard, Reliability Standard EOP-012-1, in 2022 under Project 2021-07 Extreme Cold Weather Grid Operations, Preparedness, and Coordination. The purpose of this project was to address standards-related recommendations from the Federal Energy Regulatory Commission (FERC)/NERC/Regional Entity staff review of operations during the February 2021 Winter Storm Uri event.
NERC developed Reliability Standard EOP-012-2 in 2023-2024 to address Commission directives from the
February 2023 order approving Reliability Standards EOP-012-1 and EOP-011-3. In the February 2023 Order, the Commission directed that NERC revise EOP-012-1 to clarify the applicability of the standard's requirements for generator cold weather preparedness, further define the circumstances under which a Generator Owner may declare that constraints preclude them from implementing one or more corrective actions to address freezing issues, and to shorten the implementation timeline so cold weather reliability risks would be addressed more quickly.
On June 27, 2024, FERC issued an
order approving Reliability Standard EOP-012-2. While finding Reliability Standard EOP-012-2 represented an improvement over the prior version and addressed many of its concerns, FERC found the standard requires further improvement to address certain concerns remaining from its February 2023 order. FERC therefore directed NERC to revise the standard in five areas and to submit a revised standard within nine (9) months of the date of the order, or by March 27, 2025.
Standard Affected:
EOP-012-2
Purpose/Industry Need
The purpose of this project is to address the directives identified by FERC in its June 27, 2024 order approving Reliability Standard EOP-012-2 and directing further modifications.
N. Am. Elec. Reliability Corp., 187 FERC ¶ 61,204 (2024), available
here. In that order, FERC found that further improvements needed to be made to address ambiguous language and address other reliability gaps/implementation issues in the standard and related definitions to fully address issues first raised in the Commission's February 2023 Order approving EOP-012-1. FERC directed that NERC submit the modifications within 9 months of the date of the order, or by March 27, 2025.
Proposed Project Timeline
The project timeline is listed below for
industry awareness. This table will be updated with any changes as the
project progresses.
Process Steps |
Dates
|
Notes |
Drafting Team members seated |
08/21/2024 |
Standards Committee (SC) August meeting
|
Standards Committee Executive Committee (SCEC) authorize revisions
|
09/05/2024
|
SCEC Special Call
|
SC approval of initial ballot
|
10/16/2024
|
SC October Meeting
|
Initial Ballot
|
10/17/24–11/05/24
|
20-day initial ballot and comment period per waiver approved at July SC meeting
|
First Additional Ballot
|
12/3/24–12/20/24
|
18-day additional ballot and comment period per waiver
|
Consideration of 321 Action
|
01/02/25–01/08/25
|
Based on additional ballot results, NERC staff will consider the comments received and if 321 action should be proposed to the NERC Board to meet the FERC deadline.
|
Second Additional Ballot
|
01/29/25–02/12/25
|
15-day additional ballot and comment period per waiver
|
Final Ballot
|
03/03/25–03/07/25
|
5-day final ballot per waiver
|
NERC Board Approval
|
TBD
|
Anticipated NERC Board approval in mid-March
|